HAL commits to deliver 16 to 18 Tejas Mk-1A jets to IAF by March 31, 2027

The Air Force will accept the aircraft without relaxing capability requirements, officials said, as deliveries run nearly two years behind schedule.

Hindustan Aeronautics Ltd (HAL) has committed to delivering 16 to 18 Tejas LCA Mk-1A fighters to the Indian Air Force (IAF) by March 31, 2027, officials familiar with the discussions said on Monday.

The assurance was given at a review meeting at Air Headquarters on November 16, according to Hindustan Times. Those present included Air Chief Marshal Ashutosh Dixit, the IAF chief, and Ravi K, HAL's chairman and managing director.

One official, who asked not to be named, said all hardware-related issues, including those linked to weapons trials, have been resolved. "Remaining software-related issues, including those concerning the radar, are in the final stages of resolution," the official said.

The IAF will take the aircraft without granting concessions on capability requirements, the report said. An HAL official said the company is also not seeking any concessions.

HAL will begin the documentation process at the same time. It will approach the Bengaluru-based Centre for Military Airworthiness and Certification (CEMILAC) for the release to service document, and seek a signal-out certificate from the Directorate General of Aeronautical Quality Assurance. These documents authorise the user to operate a new air system within specified conditions and approved flight envelopes.

The IAF placed two orders with HAL for 180 Mk-1A jets worth a combined ₹1.1 lakh crore. The first, for 83 aircraft, was signed in February 2021, and the second, for 97, in September 2025.

Deliveries under the first order were due to start in March 2024. That date was missed because of several factors, including GE Aerospace's inability to supply F404-IN20 engines on time and delays in securing key certifications. HAL now aims to execute the 2021 order in three to four years. Deliveries under the second contract are expected to begin in 2027-28 and conclude in six years.

The IAF operates 29 fighter squadrons against an authorised 42.5. It currently flies 38 LCA Mk-1 aircraft. The Mk-1A is meant to replace the MiG-21s, which retired last year after more than six decades of service.

Dixit took over as chief on October 31 and has named the Mk-1A, the LCA Mk-2 and the advanced medium combat aircraft programmes as top priorities. HAL has joined the front, centre and rear fuselage sections of the Mk-2 and is targeting a first ground run by March 2027, with a maiden flight later that year. The IAF will now move a case for Mk-2 procurement.

Background

The first Mk-1A order, signed in February 2021, called for deliveries to begin in March 2024. Late engine supply from GE Aerospace and delays in certification pushed the schedule back by nearly two years.

Why it matters

The IAF is short of fighter squadrons, and the Mk-1A is intended to replace the retired MiG-21s and rebuild its strength.